Construction Information


Week of July 15 Construction Activities:
  • Monday, July 16 - Thursday, July 19
    • Northbound I-25 between RidgeGate Parkway and Lincoln Avenue  
      • From 8 p.m. to 5:30 a.m. - Various double and triple lane restrictions for bridge work
    • Southbound I-25 between C-470 and RidgeGate Parkway
      • From 9 p.m. to 5:30 a.m. - Various double lane restrictions for bridge work
Ongoing traffic impacts
  • Through summer 2018
    • Trainstation Circle East at Sky Ridge Avenue is closed for the installation of the track crossing, gates, signals and associated road work. Trainstation Circle West remains open and business/residential access is maintained. 

Encourage your neighbors and co-workers to sign up for Southeast Rail Extension updates.

Get More Information:

Email: se-corridor@rtd-denver.com

Construction Information Line: (720) 643-2300


Construction activities are weather dependent and subject to change.


The Southeast Rail Extension Project will expand the Southeast Rail Line 2.3 miles from Lincoln Station to RidgeGate Parkway in Lone Tree. The expansion encompasses three new stations as follows: the Sky Ridge Station and Kiss-n-Ride near Sky Ridge Medical Center; a second Kiss-n-Ride at the future Lone Tree City Center Station; and a 1,300-space Park-n-Ride at the RidgeGate Parkway Station. The 2.3-mile extension includes a 5-span, 620-foot-long bridge over Lincoln Avenue; an 11-span, 1,397-foot-long bridge over I-25 and a 4-span, 506-foot-long bridge over RidgeGate Parkway.