Printable Version Send to Printer

Construction Information


Week of April 15 Construction Activities:

Ongoing traffic impacts
  • Through mid-May 2018
    • Trainstation Circle East at Sky Ridge Avenue is closed for the installation of the track crossing, gates, signals and associated road work. Trainstation Circle West remains open and business/residential access is maintained. 

Encourage your neighbors and co-workers to sign up for Southeast Rail Extension updates.

Get More Information:

Email: se-corridor@rtd-denver.com

Construction Information Line: (720) 643-2300


Construction activities are weather dependent and subject to change.


The Southeast Rail Extension Project will expand the Southeast Rail Line 2.3 miles from Lincoln Station to RidgeGate Parkway in Lone Tree. The expansion encompasses three new stations as follows: the Sky Ridge Station and Kiss-n-Ride near Sky Ridge Medical Center; a second Kiss-n-Ride at the future Lone Tree City Center Station; and a 1,300-space Park-n-Ride at the RidgeGate Parkway Station. The 2.3-mile extension includes a 5-span, 620-foot-long bridge over Lincoln Avenue; an 11-span, 1,397-foot-long bridge over I-25 and a 4-span, 506-foot-long bridge over RidgeGate Parkway.









© 2018 All Rights Reserved.
Web Site Designed By ProjectWest