Area 3 Construction



Perry Station - Auraria Station
Punchlist work continues at Perry Station. At Knox Station, crews will install decorative railings in mid July. Also through July, crews will complete miscellaneous items on the Tennyson Bridge. 

Through early August, crews will construct the Federal detention pond, install a drainage system, and continue landscaping in the area. Work on the Decatur-Federal Station continues with installation of the driver relief station and decorative railings, and paving the plaza at the station.