Section 5: 104th Avenue to 112th Avenue


Construction Information for the area between 104th Avenue and 112th Avenue

  • Crews are beginning work on a tunnel bore under Colorado Boulevard near the future 104th Avenue station. Depending on soil in the area, crews may be working past 7 p.m. with a small potential of work on Sundays for the duration of this work.
  • There may be temporary lane and sidewalk closures as needed from 8:30 a.m. to 3:30 p.m.  for the construction of the commuter rail bridge over 104th Avenue. These will occur between Steele Street and Fox Run Parkway.
  • There will be heavy drainage and earthwork operations along the RTD guideway between 104th Avenue and 112th Avenue. The area will be fenced off, for safety purposes, please refrain from entering the work zone at all times while this work continues through the end of the year. The bike path will remain open.
  • There will be alternating lane closures at the railroad crossing on 112th Avenue between Irma Drive and York Street daily from 8:30 a.m. to 3:30 p.m.